Qus:1 Write short notes on:
- Kano model
- Differences between a sponsor’s view and project’s view in a project balance sheet
- Triangular distribution
- Organisational break down structure
Answer:
Kano model:
In comparison to the previous two models, the Kano model is narrow in its approach. Its primary focus is on the customer
Qus:2 Discuss capital budgeting in project management.
- Describe use of capital budgeting to an organisation in terms of undertaking multiple projects
- Explain the importance of capital budgeting in project selection
- Discuss the aspects of capital budgeting that an organisation should consider while selecting a project.
Answer:
Describe use of capital budgeting to an organisation in terms of undertaking multiple projects:
An organisation undertakes multiple projects with different capital requirements and rates of returns. For instance, some projects may need investment over a longer period of time, whereas others need investments
Qus:3 Write short notes on:
- Rolling wave planning
- Time centric earned value
Answer:
Rolling wave planning:
Rolling wave planning is an iterative planning in which work to be accomplished in the near term is planned in
Qus:4 Describe the various cost incurred in a project. Describe the applications of three – point estimates.
- Discuss the THREE types of costs incurred in a project
- Discuss the applications of three – point estimates.
Answer:
Discuss the THREE types of costs incurred in a project:
The THREE types of costs incurred in
Qus:5 Explain the six sigma methodologies.
- Discuss the 2 six sigma project methodologies
- Compare the 2 six sigma project methodologies
Answer:
Discuss the 2 six sigma project methodologies:
TheDMAIC project methodology has the following five phases:
- Define: It includes defining and analysing the problem and understanding the voice of the customer,
Qus:6 Discuss the time and materials contract.
Solve the following problem
Consider a time and materials contract as follows:
Labour is billed according to the following schedule
1 software engineer: $45/hr
1 tester: $ 45/hr
1 senior software engineer: $65/hr
Material is billed according to the following schedule:
Cost of materials + 30 % profit/overhead
Actual cost of the material is $2140
Calculate the material cost, calculate the contract payable
- Describe the time and materials contract
- Calculation of material cost
- Calculation of contract payable
Answer:
Describe the time and materials contract:
The time and materials contract is a cross between FP and CP contracts. It is opposed to FP contracts in which the buyer agrees to pay the contractor a lump sum for performance regardless of what the contractors pay their employees, sub-contractors, and suppliers. This is the most risk-free type of contract. In this type of contract, the time and material used for the project are priced. Thus, the contractor only requires to know the time and