6. A project is composed of 9 activities the three estimates of time in weeks for the activities are given below in the following table. a. Draw a PERT Network b. Determine the expected time and variance for each activity c. Determine earliest and latest occurrence time of each event d. Determine the critical path for the network A a. For correctly drawing the network diagram b. For determining the expected time and variance for each activity c. For determining the earliest and latest occurrence time of each event d. For identifying the correct critical path