Q.1 Define activity, event, and path as used in network development. What is a dummy activity? Describe the CPM model.

January 08, 2013 By: Meliza Category: 1st SEM

Answer : Activity : It is physically identifiable part of a project which require time and resources for its execution. An activity is represented by an arrow, the tail of which represents the start and the head, finish of the activity.

Event: The beginning and end points of an activity are called events or nodes. Event is a point in time and does not consume any resources.

 

The critical path : is determined by adding the times for the activities in each sequence and determining the longest path in the project. The critical path determines the total calendar time required for the project. If activities outside the critical path speed up or slow down (within limits), the total project time does not change. The amount of time that a non-critical path activity can be delayed without delaying the project is referred to as slack time.

 

Dummy activity : An activity, which only determines the dependency of one

activity on the other, but does not consume any time, is called a dummy activity.

Logic Dummies

When the arrow diagram was developed, there were two important problems associated with the method. The first problem is that, since an arrow served to represent both the sequence and duration of an activity, there are cases where showing sequence with a single arrow is inadequate. The diagrams below shows several examples where a single activity arrow cannot graphically express the sequence needed in an activities list.

The first example shows how Arrow Diagramming has problems representing a sequence of activities where sets of activities share some, but not all, of the prior activities. In this example, Activity C has a prior of A and Activity B has both A and B as priors.

Activity Prior Activity
A None
B None
C A
D A, B

 

 

Notice that when we try to create an Arrow Diagram with this pattern the standard notation shown in the figure below is incorrect.

 

The developers of the Arrow Diagram created the “logic dummy.” The logic dummy, an activity with zero duration, links together activities whose sequence would otherwise not be shown. To designate the dummy activity, a dashed arrow is used. As shown on the figure below, the logic dummy is used to show the sequence between activity A and D without the problem of linking Activity B with Activity C. One way to know if a logic dummy is needed is to look at the activity list and find those activities that share some, but not the entire set of prior activities.

 

Logic dummies are quite versatile. Consider the example schedule shown below. Notice that Activities D, E, and F do not all share the same set of prior activities. As a result, two logic dummy activities are needed to properly show the sequence of tasks on this project.

Activity Prior Activity
A None
B None
C None
D A, B
 

Dear Students,

Get your assignments from Our ESTEEMED ORGANIZATION smumbaassignment.com

Just email to kvsude@gmail.com  or  S M S  to +91 9995105420.

message Format – SMU MBA <Name> <E-MAIL ID> <SEM ? >  To +91 9995105420 , we will reach back you with in 24H

Or Directly call our Middle East Office +974 55702886 .

More Info, Kindly visit  smumbaassignment.com

Best Regards, Admin

smumbaassignment.com

 

E

B
F B, C

 

 

Another example where logic dummies are needed is shown below. Notice that Activities C, D, and E do not share the same set of prior Activities. Since Activities C, D, and E do not share both Activities A and B as priors, logic dummies are needed to properly show the sequence using an arrow diagram.

Activity Prior Activity
A None
B None
C A
D A, B
E B

 

While the logical dummy is a very useful tool to allow the arrow diagram to show all the required sequence contained in a set of activities, the logical dummy should only be used when necessary to show the proper sequence. The figure below gives an example of when not to use the logical dummy.

 

In the diagram above, only prior activity to Activity D is Activity A. In this case a logic dummy is not needed between Activity A and Activity D. Logic dummies are one of the most common problem areas in the Arrow Diagramming Method. In the next section, we introduce the other area that causes problems with Arrow Diagramming, the numbering dummy.

 

 

 

CPM.:

1. CPM is activity oriented i.e., CPM network is built on the basis of activities.

2. CPM is a deterministic model. It does not take into account in uncertainties involved in the estimation of time.

3.

CPM places dual emphasis on project time as well as cost and finds the trade off. between project time and project cost.

4. CPM is primarily used for projects which are repetitive in nature and comparatively small in size.

 